Objectives and Results

The objective is the development of submodels for cell stacking machines. Optimised solutions for machine design and operation will be developed as a result.

Contents and Approach

-    Development and validation of various sub-models of a cell stacking machine
-    Cross-linking of the models
-    Derivation of optimisation approaches

Project Volume

4 Mio. €